(Archived) Development Timeline

Just to remind you what the project names mean.

Snorlax -> Main Website
Articuno -> Dashboard
Latias -> Android app
Latios -> iOS app
Magneton -> API
Ditto -> Admin Console

July

By the end of July we should have:

  • Placeholder/promotion websites up for Snorlax and Articuno.
  • Magneton should have the Newsletter feature complete along with unit tests and authentication.
  • Latias & Latios should be done with the prototype Map feature.
  • Ditto should have a skeleton complete.

August

By the end of August we should have:

  • Pre-sponsor website up for Snorlax
  • Application form and Accounts ready on Snorlax
  • Map feature on Articuno
  • Sign in and Profile display on Articuno
  • Sign in and Profile display on Latias & Latios
  • Magneton: Account Management (registration, password reset, etc.), Application, and Profile API
  • Map Management feature on Ditto

September

By the end of September we should have:

  • Full website ready (up at Marketing's discretion i.e. once we have sponsors to show) for Snorlax
  • Updates feature and Schedule feature done on Articuno
  • Updates feature and Schedule feature done on Latias & Latios
  • Announcements API and Schedule API done on Magneton

October

All non-frill features should be complete by the end of October Oct 7: Renew website domain.

November

Nov 26: Event test run

December

TBD Launch mobile apps

January


* Tenative